How long does it take to plug a data centre into the grid?

Everyone publishes GPU prices. Nobody publishes whether you can get the power to run them.

2 to 773

Days to connect a medium-voltage load in Germany — depending on nothing but whose network territory you build in. Same country, same regulator, a 386× difference.

2
fastest, days
126
median, days
773
slowest, days
251
operators

Where the 251 German operators fall

under a month
25
one to four months
96
four to twelve months
104
over a year
26

26 operators take over a year. 25 take under a month. Picking the wrong side of a boundary can cost more time than the build itself.

What this number is, and isn't. Every figure here is published by the operator or regulator. The regulator publishes it per operator for reporting year 2024, updated annually. The underlying field is named minDauer — which may mean a minimum rather than an average, while the regulator's own announcement calls it an average. Read it as a typical duration, not a floor anyone can be held to.

Czechia — where you can still connect

A different measure, because Czechia publishes a different thing: capacity to draw power, banded against a 10 MW threshold, per municipality.

2,188
room above 10 MW
1,045
room up to 10 MW
798
restricted
2,227
nobody publishes

What we don't know

Listed because it's real, and because a dataset that hides its gaps isn't worth reading.

Need power sooner than this says?

Tell us where, how much, and by when. We'll put the request to operators and providers who may have capacity — including, disclosed plainly, our launch partner. If we can't help, we'll say so.

Know something we've got wrong? Corrections are the fastest way this improves, and we'd rather be corrected than confident.

The extremes

The 20 slowest and 5 fastest of 251 operators. The full set is in the dataset.

Network operatorDaysRelativeBand
EWE NETZ GmbH 773d
over a year
Stadtwerke Verden GmbH 760d
over a year
Stadtwerke Karlsruhe Netzservice GmbH 730d
over a year
Stadtwerke Soest GmbH 600d
over a year
Stadtwerke Bamberg Energie- und Wasserversorgungs GmbH 578d
over a year
Celle-Uelzen Netz GmbH 560d
over a year
Stadtwerke Neuwied GmbH 560d
over a year
Stadtwerke Witten Mittelspannungsnetz GmbH 543d
over a year
E.DIS Netz GmbH 510d
over a year
Schleswig-Holstein Netz GmbH 504d
over a year
Freiberger Stromversorgung GmbH 465d
over a year
Stadtwerke Ludwigsfelde GmbH 450d
over a year
Stromnetz Berlin GmbH 449d
over a year
Stadtwerke - Altm. Gas-, Wasseru.Elektrizitätswerke GmbH Stendal 427d
over a year
FairNetz GmbH 424d
over a year
Stadtwerke Merseburg GmbH 421d
over a year
Stadtwerke Weißenfels Energienetze GmbH 421d
over a year
Technische Werke Naumburg GmbH 421d
over a year
Stadtwerke Dülmen GmbH 412d
over a year
Stadtwerke Riesa GmbH 402d
over a year
… 226 operators between …
Netze BW GmbH 2d
under a month
Stadtwerke Lippe-Weser Service GmbH & Co. KG 2d
under a month
Stromnetzgesellschaft Herrenberg mbH & Co. KG 2d
under a month
Stadtwerke Ochtrup 3d
under a month
Stadtwerke Waiblingen GmbH 4d
under a month